Water Works Progress
S.No | Sector | Works Details | Status/Progress |
1 | G-13 | Two days water supply through distribution services to Sector G-13 has been Started | 100% completed |
2 | G-13 | Storage of water through water tankers from G-14/F-14 to Bani Chowk underground tanks | 100% completed |
3 | G-14/4 | Underground water tank capacity 0.2 (MGD) | 100% completed |
4 | G-14/4 | Connectivity with main Distribution System | 100% completed |
5 | G-14/4 | 260 water connections | 100% completed |
6 | G-14/4 | Gate Valves installed in Phase-l (StreetNo.1-25) | 100% completed |
7 | G-14/4 | Trial water supply through distribution Phase-l (Sheet No. 1-25) carried out in coordination with residents | 100% completed |
Parks
SNo | Sub -Sector | Work Area | Status/Progress |
1 | G-13/2 | Hill Park | 98% completed |
2 | G-13/2 | Park No 5 Double Road | 95% completed |
3 | G-13/2 | Park No 6 Street No 57 | 98% completed |
4 | G-13/4 | Park No 10 | 70% completed |
5 | G-13/4 | Park No 11 Street No137 | 98% completed |
6 | G-13/4 | park No 12 Street No 152 | 35% completed |
Play Grounds
S.NO | Sub-sector | Work Area | Status/Progress |
1 | G-13/1 | Model Play Ground Street. No 78 | 100% completed |
2 | G-13/2 | Play Ground No2 Cricket Ground Street No 40 | 100% completed |
3 | G-13/4 | Play Ground No2 Foot ball Ground Street No 4 | 40% completed |
4 | G-13/3 | Play Ground No 4 Street No 159 | 30% completed |